Grand River Street North, between Silver Street and Watts Pond Road in Paris, is an important route that supports residents, businesses, schools, emergency services, and future growth in north Paris. Construction on this section began in 2023 as part of a multi-year project to improve underground infrastructure, road safety, traffic flow, and walking and cycling connections.
The project is moving forward now because the County secured more than $9 million in provincial funding, helping reduce costs for local taxpayers. To receive the full benefit of this funding, the work must be substantially completed by 2028. These improvements will also helpContinue reading
Grand River Street North, between Silver Street and Watts Pond Road in Paris, is an important route that supports residents, businesses, schools, emergency services, and future growth in north Paris. Construction on this section began in 2023 as part of a multi-year project to improve underground infrastructure, road safety, traffic flow, and walking and cycling connections.
The project is moving forward now because the County secured more than $9 million in provincial funding, helping reduce costs for local taxpayers. To receive the full benefit of this funding, the work must be substantially completed by 2028. These improvements will also help prepare the area for future growth (for the next 30 years!), including a planned new school (public, elementary) and fire hall, while creating a safer and more efficient corridor for everyone who uses it.
Construction will take place in stages to help maintain traffic flow and access throughout the project.
You can expect:
Side streets will only be closed when necessary and for the shortest duration possible.
Access and safety during construction
Access to homes, businesses, the North Paris Fire Hall, and the Gilbert Water Treatment Plant will be maintained throughout construction.
Special measures will also be used near Paris District High School to support safe walking routes for students. This may include temporary signage, pedestrian controls, and protective measures where needed.
The County will continue to provide project updates and construction notices as work progresses.
Contract 1 | Contract 2 | Contract 3 |
|---|---|---|
| Timeline: Completed in 2023 and 2024 | Timeline: 2026 to 2028 | Timeline: 2026 to 2028 |
| Area: Grand River Street North from Bradbury Crescent to Hartley Avenue | Area: Grand River Street North from north of Silver Street to north of Scott Avenue | Area: Grand River Street North from north of Scott Avenue to Watts Pond Road |
Work completed:
| Planned work:
| Planned work:
|
Progress and major milestones will be posted on this page. Subscribe for updates by adding your email to the Stay Informed box on this page and click ‘Subscribe'.
Thank you to everyone who attended the Grand River Street North and Bendemere Road Public Information Open House on June 18.
More than 100 people joined us throughout the evening to learn about these important infrastructure projects, ask questions, and speak with the project teams. We appreciate the thoughtful conversations and valuable input received from the community. Your participation helps us better understand local perspectives as these projects move forward.
Project information, updates, and future notices will continue to be posted on the project pages. If you haven't already, we encourageContinue reading
Thank you to everyone who attended the Grand River Street North and Bendemere Road Public Information Open House on June 18.
More than 100 people joined us throughout the evening to learn about these important infrastructure projects, ask questions, and speak with the project teams. We appreciate the thoughtful conversations and valuable input received from the community. Your participation helps us better understand local perspectives as these projects move forward.
Project information, updates, and future notices will continue to be posted on the project pages. If you haven't already, we encourage you to subscribe to receive updates directly by email by adding your email to the Stay Informed box on this page and click ‘Subscribe'.
For more information and to subscribe for updates to the Bendemere Road project, please visit EngageBrant.ca/Bendemere.
Thank you again for your continued interest and involvement.
The County of Brant is inviting residents to attend an upcoming Public Information Open House for the Grand River Street North Improvements and Bendemere Road projects in Paris.
This drop in event will give community members an opportunity to learn more about both projects, view project information, and speak directly with members of the project teams.
Though there will not be a formal presentation, residents are encouraged to stop by anytime during the event to ask questions, shareContinue reading
The County of Brant is inviting residents to attend an upcoming Public Information Open House for the Grand River Street North Improvements and Bendemere Road projects in Paris.
This drop in event will give community members an opportunity to learn more about both projects, view project information, and speak directly with members of the project teams.
Though there will not be a formal presentation, residents are encouraged to stop by anytime during the event to ask questions, share comments, and learn more about what to expect as work moves forward.
With earlier phases of the Grand River Street North Improvements project replacing aging watermain and sanitary sewers between Trillium Way and Hartley Avenue, the County of Brant will be continuing work on Grand River Street North this spring. These upgrades are part of a long term plan to improve infrastructure, safety, and mobility in this area of Paris.
The next phase of work will focus on roadway improvements, including storm sewer installation, new roundabouts, and a multi use path.
A public open house will be held later this spring to share preliminary project details, estimatedContinue reading
With earlier phases of the Grand River Street North Improvements project replacing aging watermain and sanitary sewers between Trillium Way and Hartley Avenue, the County of Brant will be continuing work on Grand River Street North this spring. These upgrades are part of a long term plan to improve infrastructure, safety, and mobility in this area of Paris.
The next phase of work will focus on roadway improvements, including storm sewer installation, new roundabouts, and a multi use path.
A public open house will be held later this spring to share preliminary project details, estimated timelines, and possible impact. You will have the opportunity to ask questions and provide feedback directly to the project team. More information, including the date and location, will be shared closer to the end of the spring.
Construction will continue in phases. Information and updates will be shared on this page as they are available and projects subscribers will be notified directly, through email.
We invite you to subscribe for updates by adding your email to the Stay Informed box on this page and click ‘Subscribe'.
Grand River Street North has been reopened to two way traffic.
Road painting will take place on Tuesday, April 2 and Wednesday, April 3. Grand River Street North will remain open during painting but may be redirected at times so please drive carefully.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
Learn more about road closures and construction in the County of Brant.
Grand River Street North has been reopened to two way traffic.
Road painting will take place on Tuesday, April 2 and Wednesday, April 3. Grand River Street North will remain open during painting but may be redirected at times so please drive carefully.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
Learn more about road closures and construction in the County of Brant.
The intersection of Grand River Street North and Hartley Ave. has been reopened to traffic.
Grand River Street North, south of Hartley Ave. to Scott Ave. will remain closed until April 5, 2024, pending weather conditions and the availability of asphalt for restoration.
Scott Ave East of Grand River Street North will also be closed for one week commencing today, March 4, 2024 for sanitary sewer installation.

We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
The intersection of Grand River Street North and Hartley Ave. has been reopened to traffic.
Grand River Street North, south of Hartley Ave. to Scott Ave. will remain closed until April 5, 2024, pending weather conditions and the availability of asphalt for restoration.
Scott Ave East of Grand River Street North will also be closed for one week commencing today, March 4, 2024 for sanitary sewer installation.

We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated while we make important improvements to our municipal infrastructure.
Learn more about road closures and construction in the County of Brant.
The Grand River Street North and Hartley Avenue intersection will be closed beginning Tuesday, February 20.
Work Commencing: Tuesday, February 20 to Friday, March 15, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:

We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction andContinue reading
The Grand River Street North and Hartley Avenue intersection will be closed beginning Tuesday, February 20.
Work Commencing: Tuesday, February 20 to Friday, March 15, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:

We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated while we make important improvements to our municipal infrastructure.
Learn more about road closures and construction in the County of Brant.
Please note the road closure on Grand River Street North between Scott Avenue and Hartley Avenue has been extended until approximately March 1. This extension is due to weather and sequencing of works on site. We apologize for the inconvenience.
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:
Please note the road closure on Grand River Street North between Scott Avenue and Hartley Avenue has been extended until approximately March 1. This extension is due to weather and sequencing of works on site. We apologize for the inconvenience.
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:

We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511(External link) for the most up-to-date traffic information regarding road construction and closures.
It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated while we make important improvements to our municipal infrastructure.
Learn more about road closures and construction in the County of Brant.
Location: Grand River Street North between Scott Avenue and Hartley Avenue
Dates: Monday, January 22 to Friday, January 26, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Note:
We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511(External link) forContinue reading
Location: Grand River Street North between Scott Avenue and Hartley Avenue
Dates: Monday, January 22 to Friday, January 26, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Note:
We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511(External link) for the most up-to-date traffic information regarding road construction and closures.
It is our goal to minimize any inconvenience to our residents. Your patience through any disruption will be greatly appreciated while we make important improvements to our municipal infrastructure.
Learn more about road closures and construction in the County of Brant.
Grand River Street North Construction will return this Monday, January 8, 2024, and a portion of Grand River Street North will be closed.
Location: Grand River Street North between Scott Avenue and Woodslee Avenue
Work Commencing: Monday, January 8 to Friday, March 29, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:
We remind the public that businessesContinue reading
Grand River Street North Construction will return this Monday, January 8, 2024, and a portion of Grand River Street North will be closed.
Location: Grand River Street North between Scott Avenue and Woodslee Avenue
Work Commencing: Monday, January 8 to Friday, March 29, 2024
Work Performed by: Regional Sewer and Watermain Ltd for County of Brant
Reason: Trunk Sewer and Watermain Replacement
Notes:
We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511(External link) for the most up-to-date traffic information regarding road construction and closures.
Thank you for your patience and understanding as we make important improvements to our municipal infrastructure.
Grand River Street North is now open to traffic in both directions from Silver Street to Scott Avenue.
In the new year, beginning approximately January 8, 2024, Grand River Street North will be closed in both directions from Scott Avenue to Woodslee Avenue. A detour route will be posted from Woodslee Avenue to Lee Avenue to Scott Avenue to access Grand River Street North to Pinehurst Road and vice versa. It is anticipated that this phase of work (referred to as Phase 1A) will be completed by the end of February 2024.
Following completion of Phase 1A, Phase 1B willContinue reading
Grand River Street North is now open to traffic in both directions from Silver Street to Scott Avenue.
In the new year, beginning approximately January 8, 2024, Grand River Street North will be closed in both directions from Scott Avenue to Woodslee Avenue. A detour route will be posted from Woodslee Avenue to Lee Avenue to Scott Avenue to access Grand River Street North to Pinehurst Road and vice versa. It is anticipated that this phase of work (referred to as Phase 1A) will be completed by the end of February 2024.
Following completion of Phase 1A, Phase 1B will commence. Phase 1B includes the closure of Pinehurst Road and Grand River Street North, in both directions, from Hartley Avenue to Scott Avenue. A detour route will be shared closer to the construction start date. It is anticipated that Phase 1B will be completed by the end of March 2024.
We remind the public that businesses remain open during construction. Please show your support and shop local.
Please refer to Municipal 511 for the most up-to-date traffic information regarding road construction and closures.
Thank you for your patience and understanding as we make important improvements to our municipal infrastructure.
Work includes the replacement of watermain and sanitary sewers from 100 metres south of Trillium Way to Hartley Avenue.
Work on Grand River Street North from the south limit to Scott Avenue, will be completed and reopened before the end of December 2023.
Watermain and sanitary sewer construction continue to completion at Hartley Avenue.
An open house took place June 2026.
Construction is expected to start Fall 2026 between Silver St and Watts Pond Rd.
June 18 Open House Presentation Boards (4.97 MB) (pdf)
2026 Contract #2
2026 Contract #3
Recommended Plan for Grand River Street North (18.1 MB) (pdf)
Final design 3D rendering of the new fire hall (703 KB) (pdf)
Image of Grand River St N (59.3 MB) (pdf)
Image of Ann Wilson Way (20.3 MB) (pdf)
Quick facts for Grand River St N (252 KB) (pdf)
| Phone | 519-44BRANT (519-442-7268) |
| devid.mellor@brant.ca |
| Phone | 519-44BRANT (519-442-7268) |
| mark.eby@brant.ca |
| Phone | 519-44BRANT (519-442-7268) |