Cainsville Water, Wastewater, Stormwater Study

Share Cainsville Water, Wastewater, Stormwater Study on Facebook Share Cainsville Water, Wastewater, Stormwater Study on Twitter Share Cainsville Water, Wastewater, Stormwater Study on Linkedin Email Cainsville Water, Wastewater, Stormwater Study link

The County of Brant would like to thank residents and business owners for engaging with us as we considered alternatives to provide water, wastewater, and stormwater servicing in Cainsville. This included expanding services to currently unserviced areas within the settlement boundary. The study identified the preferred alternatives to prepare for long-term growth through to the year 2051.

Design of the project is underway and construction is anticipated to start in 2027. Map of Cainsville Study AreaCainsville Study Area Map

Infrastructure will include:

  • Watermain
  • Sanitary sewers
  • Stormwater
  • Fire service upgrades
  • Road surfacing
  • Intersection improvements.

Stay informed

Subscribe for project updates by adding your email to

The County of Brant would like to thank residents and business owners for engaging with us as we considered alternatives to provide water, wastewater, and stormwater servicing in Cainsville. This included expanding services to currently unserviced areas within the settlement boundary. The study identified the preferred alternatives to prepare for long-term growth through to the year 2051.

Design of the project is underway and construction is anticipated to start in 2027. Map of Cainsville Study AreaCainsville Study Area Map

Infrastructure will include:

  • Watermain
  • Sanitary sewers
  • Stormwater
  • Fire service upgrades
  • Road surfacing
  • Intersection improvements.

Stay informed

Subscribe for project updates by adding your email to the Stay Informed box on this page and click ‘Subscribe’.

Comment and Questions

County of Brant Staff aim to maintain a respectful and constructive dialogue with the public through all forms of communication. We understand and appreciate that people will have differing opinions and concerns, and welcome all constructive criticism, feedback, questions, and comments in a respectful and constructive manner.

Questions and feedback about the Cainsville water, wastewater and stormwater management Environmental Study Report are welcome until Friday, May 17, 2024. We will do our best to respond within 3 business days.  

You need to be signed in to add your question.

  • Share Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it. Sincerely, Stephan Pelchat on Facebook Share Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it. Sincerely, Stephan Pelchat on Twitter Share Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it. Sincerely, Stephan Pelchat on Linkedin Email Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it. Sincerely, Stephan Pelchat link

    Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it. Sincerely, Stephan Pelchat

    StephanP asked over 2 years ago

    Thanks for your interest in this study. Presentation material from the June 2023 public meeting can be found on the Engage Brant webpage, here: https://engagebrant.ca/cainsvillewater. See the Documents section on the right hand side of the page.

    Thank you,

    M. Maxwell, P. Eng

    County of Brant

  • Share Will Brant School Road be included? on Facebook Share Will Brant School Road be included? on Twitter Share Will Brant School Road be included? on Linkedin Email Will Brant School Road be included? link

    Will Brant School Road be included?

    deej2005 asked over 2 years ago

    Thanks for your interest in this study. Some lands on the south side of Brant School Road are within the Cainsville Settlement Boundary and a plan to extend municipal water and wastewater services has been included in the recommended alternatives. The June 21, 2023 presentation material is now available on Engage Brant. Please feel free to submit comments on the proposed recommended alternatives.

    Thank you,

    M. Maxwell, Project Engineer 

    County of Brant

  • Share What is the timing and cost? on Facebook Share What is the timing and cost? on Twitter Share What is the timing and cost? on Linkedin Email What is the timing and cost? link

    What is the timing and cost?

    Richard asked over 4 years ago

    Thanks for your question. We’re currently still reviewing the various water, wastewater and stormwater options, so detailed cost estimates have not been developed yet. We will be developing cost estimates for the various options and presenting them at a second public meeting that will occur in the spring of 2022. Once the preferred alternatives are confirmed and the Class EA study is finalized, the County will immediately proceed to detailed design and construction of the initial phases.

    M. Maxwell, P. Eng.

    County of Brant

  • Share Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development. It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now. on Facebook Share Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development. It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now. on Twitter Share Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development. It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now. on Linkedin Email Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development. It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now. link

    Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development. It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now.

    deej2005 asked over 4 years ago

    Thank you for your comments. We agree that the natural environment and safe drinking water should be protected. All alternatives that are considered in the current study for Cainsville will be evaluated against these two very important criteria, among others. Please feel free to join us at the October 28th virtual public meeting.

    M. Maxwell, P. Eng.

    County of Brant

Page last updated: 19 Feb 2026, 12:48 PM