Share on FacebookShare on TwitterShare on LinkedinEmail this link
The County of Brant invites you to engage with us as we consider alternatives to provide water, wastewater, and stormwater servicing in Cainsville. This includes expanding services to currently unserviced areas within the settlement boundary. The study will identify the preferred alternatives to prepare for long-term growth through to the year 2051.
The study will be completed as a Schedule ‘C’ project in accordance with the Municipal Class Environmental Assessment process (Municipal EngineersCainsville Study Area Map Association, June 2000, as amended in 2015). The study will also be guided by the County of Brant Official Plan and the BoundaryContinue reading
The County of Brant invites you to engage with us as we consider alternatives to provide water, wastewater, and stormwater servicing in Cainsville. This includes expanding services to currently unserviced areas within the settlement boundary. The study will identify the preferred alternatives to prepare for long-term growth through to the year 2051.
The study will be completed as a Schedule ‘C’ project in accordance with the Municipal Class Environmental Assessment process (Municipal EngineersCainsville Study Area Map Association, June 2000, as amended in 2015). The study will also be guided by the County of Brant Official Plan and the Boundary Adjustment Agreement with the City of Brantford.
Stay informed
Scroll down to see the news feed of information as well as opportunities to engage, a timeline of events and more.
Subscribe for updates and be the first to learn more information about this project. Add your email to the Stay Informed box on this page and click ‘Subscribe’.
For further information relating to this project or to be added to the project mailing list, please contact either of the following members of the study team:
Comments and information regarding this Municipal Class Environmental Assessment are being collected in accordance with the Municipal Freedom of Information and Protection of Privacy Act. With the exception of personal information, all comments will become part of the public record.
County of Brant Staff aim to maintain a respectful and constructive dialogue with the public through all forms of communication. We understand and appreciate that people will have differing opinions and concerns, and welcome all constructive criticism, feedback, questions, and comments in a respectful and constructive manner.
Questions and feedback about the Cainsville water, wastewater and stormwater management Environmental Study Report are welcome until Friday, May 17, 2024. We will do our best to respond within 3 business days.
Share on FacebookShare on TwitterShare on LinkedinEmail this link
Good evening, just wondering if it would be possible to get the information from the meeting on June 21, 2023 regarding city water and sewage on Blossom Ave. I was unfortunately not able to attend the meeting but would like to know the outcome of it. If someone could tell me where to get that information I would really appreciate it.
Sincerely,
Stephan Pelchat
Stephan
asked
9 months ago
Thanks for your interest in this study. Presentation material from the June 2023 public meeting can be found on the Engage Brant webpage, here: https://engagebrant.ca/cainsvillewater. See the Documents section on the right hand side of the page.
Thank you,
M. Maxwell, P. Eng
County of Brant
Share on FacebookShare on TwitterShare on LinkedinEmail this link
Will Brant School Road be included?
deej2005
asked
10 months ago
Thanks for your interest in this study. Some lands on the south side of Brant School Road are within the Cainsville Settlement Boundary and a plan to extend municipal water and wastewater services has been included in the recommended alternatives. The June 21, 2023 presentation material is now available on Engage Brant. Please feel free to submit comments on the proposed recommended alternatives.
Thank you,
M. Maxwell, Project Engineer
County of Brant
Share on FacebookShare on TwitterShare on LinkedinEmail this link
What is the timing and cost?
Richard
asked
over 2 years ago
Thanks for your question. We’re currently still reviewing the various water, wastewater and stormwater options, so detailed cost estimates have not been developed yet. We will be developing cost estimates for the various options and presenting them at a second public meeting that will occur in the spring of 2022. Once the preferred alternatives are confirmed and the Class EA study is finalized, the County will immediately proceed to detailed design and construction of the initial phases.
M. Maxwell, P. Eng.
County of Brant
Share on FacebookShare on TwitterShare on LinkedinEmail this link
Our preferred drinking water source is the one we have now: our well. But there is t unlimited water in the water table. Developments must be done in a sustainable way without compromising our water supply with unrestricted or aggressive development.
It’s far more important to have high speed internet and natural gas infrastructure. Alternatively, give us options for solar installation so we are not so dependent on the unstable grid we’re on now.
deej2005
asked
over 2 years ago
Thank you for your comments. We agree that the natural environment and safe drinking water should be protected. All alternatives that are considered in the current study for Cainsville will be evaluated against these two very important criteria, among others. Please feel free to join us at the October 28th virtual public meeting.
Click here to play video
Cainsville Water, Wastewater, and Storm Water Servicing Class EA
Cainsville Water, Wastewater, and Storm Water Servicing Class EA
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends