Downtown Paris Master Plan: The Downtown Dig

Scroll down to learn more about the project, stay up-to-date with the project's news feed including ways to engage and more!

Big changes came to Paris in 2025 with the Downtown Dig! This once-in-a-lifetime project replaced essential infrastructure.

Reconstruction includes NEW:

  • Infrastructure (water, sewers) and upgraded utilities (gas, electrical etc.) under the roads
  • Road construction
  • Sidewalks (widened)
  • Streetscape such as lamp posts, benches, trees
  • Accessibility features
  • Digital features
  • Climate resiliency

The downtown angled parking was converted to parallel parking. The Downtown Paris Master Plan included a parking structure in the municipal lot by Council Chambers. This plan is being

Scroll down to learn more about the project, stay up-to-date with the project's news feed including ways to engage and more!

Big changes came to Paris in 2025 with the Downtown Dig! This once-in-a-lifetime project replaced essential infrastructure.

Reconstruction includes NEW:

  • Infrastructure (water, sewers) and upgraded utilities (gas, electrical etc.) under the roads
  • Road construction
  • Sidewalks (widened)
  • Streetscape such as lamp posts, benches, trees
  • Accessibility features
  • Digital features
  • Climate resiliency

The downtown angled parking was converted to parallel parking. The Downtown Paris Master Plan included a parking structure in the municipal lot by Council Chambers. This plan is being re-formulated.

While construction is challenging for residents and businesses, the end result is a more vibrant, accessible and functional downtown Paris for decades to come. Together, we can keep our community strong. Remember to Shop Local and support our downtown businesses throughout the transformation!

Background

In 2025, downtown Paris on Grand River Street North (between the Nith River Bridge and William Street) underwent major reconstruction. This level of construction in a downtown occurs every 75-100 years. It included replacing critical major infrastructure which ensures the longevity of the thriving downtown for decades to come. The final result is beautiful, functional and accessible for all.

In 2026, the remaining work for the downtown on Grand River Street North will be completed. This will include finishing concrete and brick work, hydro servicing and adding the finishing touches such as new benches. The Grand River Street North and William Street intersection will also be fully re-constructed. Updates will be provided to the community in spring 2026 about detours and traffic impacts.

The Downtown Dig impact and timelines:

  • 2024, 2025: West River Street (Mechanic Street to Broadway Street West)
  • 2025, 2026: Grand River Street North (between the Nith River Bridge and north of William Street)
  • 2027-2029: Mechanic Street (between Grand River Street North to West River Street) - full underground replacement and street scaping
  • 2027-2029: Broadway Street West (between Mechanic Street to William Street)
  • 2027-2029: William Street (between Broadway Street to Grand River Street North)
  • Municipal parking lot behind Council Chambers (future update pending)

*Proposed location, additional design work will be done to ensure suitability.

For more information on The Downtown Dig, we also invite you to visit brant.ca/TheDowntownDig.

FAQs

We have included a list of other frequently asked questions to help answer some questions you may have about the project.

Support for businesses

The County of Brant is committed to working closely with downtown businesses before and during the construction. The Downtown Paris BIA Management Board has voiced their support for the downtown revitalization noting it may be a challenging business year but the lasting result will be worth it to ensure a thriving downtown for the future. The County of Brant and Downtown Paris BIA will encourage residents to “Shop Local” and support the downtown businesses. Several events will be planned to engage the community and businesses during the construction.

Businesses are invited to learn more about this project and provide feedback through the Business Downtown Dig Engage page.

Stay informed

Subscribe to this project and be the first to receive updates as they are available. Add your email to the Stay Informed box on this page and click ‘Subscribe'.

  • Progress Update - October 24, 2025

    supporting image

    The Downtown Dig is truly taking shape and work is continuing to progress well.

    Current update

    • Street light work conduit - 95% complete
    • Hydro work:
      • vault work southeast of Grand River Street North and William St. - 100%
      • primary line - 95% complete
      • service connection to buildings - 30% complete (this is continuing to go slower than expected)
    • Road base gravel placement - 90% complete
    • East side curb - 95% complete
    • Landscaping:
      • soil cells - 100%
      • planter box - 40%

    Next two (2) weeks

    • Street light work continues. Slight delay with the delivery of the street light poles. Installation on the west side of Grand River Street North is expected shortly.
    • Hydro work:
      • primary line work continues
      • service connections to buildings continues
    • Road work:
      • road base gravel to be completed
      • base asphalt paving to commence
    • Sidewalk and amenity space
      • the sidewalk on the east side is expected to commence
      • brick work to commence
    • Landscaping
      • planter box continues

    Re-openings

    The Contractor is working hard to ensure the area south of Cobblestone Commons will be fully completed including street scaping by November 7, 2025. This will allow the public to observe the Remembrance Day service at the Paris Cenotaph. This will include the re-opening of:

    • the Nith River Bridge,
    • the Mechanic Street and Grand River Street North intersection.

    As well, the Contractor is continuing to push to complete as much work as possible (weather depending). The plan is to demobilize from the site prior to Jingle Bell Night on November 21, 2025. This will allow the re-opening of Grand River Street North. As planned, additional work will remain to be completed in the spring/early summer of 2026 on Grand River Street North. More information about the 2026 plans will be shared in future as they are confirmed.

    Again, thank you for your patience as beautiful downtown Paris is re-constructed! Please shop local and support our local businesses!

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe to this page for project updates and explore detour maps, phase details, and more. Add your email address to the Stay Informed box on this page and click ‘Subscribe'.
    ✔ Visit brant.ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at municipal511.ca.

  • Progress Update - October 17, 2025

    supporting image

    Exciting things are happening in Downtown Paris! Visit the downtown as things take shape.

    What’s happening downtown?

    This week:

    • Hydro service connections began on the east side of Grand River Street North, south of Cobblestone Commons.
    • Hydro work will continue at the corner of William Street and Grand River Street North to pull the hydro around the corner to continue service connections.
    • Preparation for streetlights continue.
    • Planters are being installed on the west side of Grand River Street North and concrete underlay for brick work continues.
    • Preparation for curb installation on the east side of Grand River Street North has begun.

    Next week:

    • Planter and concrete underlay for the brick work will continue.
    • The curb will be poured on the east side of Grand River Street North.
    • The sidewalk south of Cobblestone Commons on the east side of Grand River Street North will be poured.
    • Work will be heavily focused on the area south of Cobblestone Commons.

    Delivery of streets lights is expected the week of October 27, 2025.

    Shop local

    Visit the downtown to shop local, support businesses, and cheer on the contractors as the new downtown takes shape!

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe to this page for project updates and explore detour maps, phase details, and more. Add your email address to the Stay Informed box on this page and click ‘Subscribe'.
    ✔ Visit brant.ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at municipal511.ca.

  • Downtown Dig Progress Update - October 10, 2025

    supporting image

    Things are happening in Downtown Paris - the Dig continues!

    Accomplishments from the last two (2) weeks include:

    • Street light conduit - 95%
    • Hydro primary line - 95%
    • Cobblestone Commons investigation for hydro - 100% complete
    • Road base gravel placement - 85% complete
    • West side curb - 100% complete
    • Landscaping - 20% complete

    Anticipated work over the next two (2) weeks include:

    • Street light work continues
      • Street light poles on west side are expected to arrive shortly and will be installed
    • Hydro
      • Primary line work continues
      • Vault work southeast of Grand River Street North and William Street to be completed
      • Service line connecting to businesses to commence October 14, 2025
    • Landscaping to continue
      • West side planter box to commence
    • Curb installation on east side to commence
    • Removal of the existing sidewalk on the east side continues

    Thank you for your continued patience! Please continue to support our community by shopping and supporting local!

    Follow the Downtown Dig on Facebook and Instagram for updates!

  • Downtown Dig Progress Update: October 3, 2025

    New developments this week include:

    Strip Drain

    The strip drain was installed on the west side of the street. The purpose of this drain is to collect and quickly remove excess water from the surface to prevent flooding, pooling, and structural damage. It is a linear drainage system, often used in modern indoor and outdoor areas, that intercepts water and channels it to an outlet.

    Roll Over Curb

    As well, the installation of the curb along the west side of the street has started. The curb will be a roll over curb. A roll over curb is sloped and creates a gradual transition between the sidewalk and street, enabling people using mobility devices like wheelchairs or strollers to pass over the curb smoothly without getting stuck. It provides improved accessibility, making public spaces accessible to a wider population, including people with disabilities, seniors, parents with strollers, and even luggage carriers.

    Cobblestone Commons

    Finally, the hydro work required in the Cobblestone Commons area may be more extensive than originally anticipated. The Contractors will work to maintain some access but at times, access may be temporarily restricted.

    Shop Local

    As always, shop local as we near the holiday season and support local businesses!

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
    ✔ Visit brant.ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at municipal511.ca.

  • Downtown Dig Progress Update: September 26, 2025

    supporting image

    Progress is happening! The sidewalk on the west side of Grand River Street North is fully installed and open to the public!

    The sidewalk on the east side of the street will be installed once hydro servicing is complete. We will keep you informed.

    Notable accomplishments and statuses:

    • West side sidewalk - 100% complete
    • West side foundation repairs - 100% complete
    • County conduit for future fibre - 100% complete
    • Hydro primary duct line - 80% complete (Hydro 60% overall)
    • Road base gravel placement - 80% complete
    • Street light conduit - 50% complete
    • West side landscaping - 50% complete


    In the coming weeks, hydro servicing, streetlight work, and landscaping will continue.

    We want to thank everyone who supported Downtown Paris BIA’s Block Party last week! It was a great success! Please continue to shop and dine local to support businesses.

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
    ✔ Visit brant.ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at municipal511.ca.

  • Silva Cells Being Installed for Trees and Planters

    Crews are installing Silva Cells in sidewalk and planter box areas as part of the Downtown Dig reconstruction. Silva Cells support healthy tree growth and help manage stormwater, on site.


    Improved Stormwater Management

    Serving a dual purpose, Silva Cells are a stormwater management feature that also supports tree growth.

    • Are a Low Impact Development (LID) stormwater management feature that act as a bioretention system under pavement. They promote groundwater infiltration and filter pollutants through the soil and root uptake.
    • They promote groundwater infiltration which reduces runoff during rainfall events.
    • They assist in stormwater management in tight urban spaces because their modular structure fits under sidewalks and planters without needing large surface basins.


    For more information on stormwater management in the County, please visit brant.ca/Stormwater.


    Supporting the County’s Climate Action Plan

    The County’s Climate Action Plan, approved in late 2024, outlines the need to adapt to our changing climate and promote environmental sustainability.

    Silva Cells support those targets by

    • supporting green infrastructure that handles water naturally, promotes stormwater infiltration and improves resilience
    • enhancing the growth and longevity of the trees to be planted downtown and supports the goal of planning 55,000 trees by 2035 on public and private lands
    • Adding trees downtown offers many benefits – they will help reduce the urban heat island effect and keep downtown cool with natural shade, while improving air quality by sequestering carbon.


    For more information on Climate Action in the County, please visit brant.ca/ClimateAction.


    Thank you for your patience as these important upgrades are made and construction continues.

    As always, we encourage you to think local and shop in Downtown Paris. The heart of our community thrives with your support!

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
    ✔ Visit www.brant.ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at www.municipal511.ca.

  • Downtown Dig Progress Update: September 12

    We’re moving into the final stages of Phase 2a and 2b of the Downtown Dig! Much of the major infrastructure work is now complete, and crews are focusing on finishing touches that will bring us closer to a renewed and revitalized downtown.

    Work done the past two weeks

    • Sanitary sewer services to buildings 100% complete
    • Remaining catchbasin installations and storm sewer system 100% complete
    • Bell works 100% complete
    • Foundation restoration 98% complete, surface parging remains
    • Other identified foundation repairs ongoing
    • Lisa's Way walkway restored, planter box area remains
    • Excavation for road base 100% complete
    • Road base gravel placement 50% complete
    • Landscaping work has commenced
    • Streetlight conduit installation has commenced
    • Hydro works Ongoing

    Next 2 weeks

    • Hydro works continue
    • Landscaping works continue
    • Streetlight conduit installation continues
    • Foundation restoration work will be complete
    • Other identified foundation repairs will be complete
    • Curb installation to commence
    • Sidewalk installation to commence.


    Thank you to our residents, businesses, and visitors for your continued patience and support throughout this project — the end result is just around the corner!

    Stay connected and informed

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
    ✔ Visit www.brant,ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at www.municipal511.ca.

  • Lisa's Way Walkway Closure

    supporting image

    Lisa’s Way walkway in Downtown Paris, located between BMO and the County of Brant Customer Service Office, is tentatively scheduled to close for concrete walkway installation from Wednesday, September 3 to Friday, September 5, 2025 (weather permitting). Updates will be shared as they become available.

    Pedestrian through access from the parking lot to Grand River Street North between 66 and 68 Grand River Street North will be unavailable.

    Detour signage to/from Grand River Street North will be posted. County of Brant public washrooms will remain open.

    Please use alternate routes to access Downtown:

    • Mechanic Street
    • William Street
    • Accessible access available via Rexall

    Thank you for your patience and understanding as we work to build a better Downtown Paris, Ontario!

    To learn more about the Downtown Dig, or view the Downtown Paris Business Directory, visit brant.ca/DowntownDig


  • Downtown Dig Progress Update - August 29

    supporting image

    Great progress is being made in Downtown Paris!

    Over the past two weeks crews have:
    ✅ Completed watermain work and fire hydrant repairs (new system is now fully operational!)
    ✅ Finished storm repairs on Lisa’s Way
    ✅ Continued important hydro and utility work

    Next 2 Weeks Ahead:
    • Continued sanitary, hydro, and Bell work
    • Catch basin lead repairs starting
    • Road building begins: excavation + base material placement
    • Concrete walkway installation is tentatively scheduled to take place on Lisa’s Way on September 3 and 4. The walkway will be closed during this time.

    During the Dig, access to your favourite businesses and establishments remains open – though occasional changes to crosswalks and sidewalks may occur due to construction.

    As always, we encourage you to think local and shop in Downtown Paris. The heart of our community thrives with your support!

    Stay connected and informed:

    ✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
    ✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
    ✔ Visit www.brant,ca/DowntownDig for additional resources
    ✔ Refer to for the most up-to-date traffic information regarding road construction and closures at www.municipal511.ca.

    Thank you for your continued patience as we move closer to a revitalized downtown!

  • Downtown Dig Progress Update - August 15

    What’s been done (last 2 weeks)

    • Watermain services (main to curbstop) - 90% completed
    • Watermain services (curbstop to building) - 50% completed
    • Sanitary services to building connections - 50% completed
    • Hydro work started


    Coming up (next 2 weeks)

    • Water services from main to curbstop continues
    • Water services from curbstop to building continues
    • Sanitary service connection to building continues
    • Hydro work continues


    Lisa's Way Update

    • Lisa's Way storm repair next week from Monday, August 18 to Thursday, August 21 (weather depending)
    • Midblock crosswalk will be shifted shortly North of current location
    • Public washrooms will be temporarily unavailable within the duration of the work and portable washrooms will be provided.
    • South row of parking behind BMO will be temporarily unavailable within the duration of the work.


    During the Dig, sidewalks, crosswalks, and access to your favourite businesses and establishments will remain open — though occasional changes may occur due to construction activities.

    As always, we encourage you to think local and shop in Downtown Paris. The heart of our community thrives with your support.


    Stay connected and informed


    Thank you for your continued patience as we work to upgrade the infrastructure in Downtown Paris.

Page last updated: 26 Mar 2026, 08:18 AM