Water Service Disruption Notice
The final connections of the watermain on Dundas Street East will begin Monday, October 26, 2026.
Details
- Monday, October 26, 2026 (7:00 am – 5:00 pm) Part 1 of the final connection of the watermain at Curtis Avenue South will be completed.
- Monday, October 26, 2026 (8:00 pm – 4:00 am) final connections of water services for Businesses will be completed.
- Delayed until further notice - final connections for residential water services. As well as the final connection of the watermain between the CN bridge and Consolidated Drive.
- Delayed until further notice - Part 2 of the final connection of the watermain at Curtis Avenue South will be completed.
Impacts
- Intersection impacts: Periodic flagging may occur at the intersection of Curtis Avenue South and Dundas Street East to access water valves.
- Road or sidewalk impacts: No change
- Noise/light: Heavy equipment and dump trucks will be operating during early morning and overnight work activities. Additional lighting will also be onsite for worker safety.
Service Disruption
- Water service will be turned off for properties on Curtis Avenue South on Monday, October 26, 2026, from 8:00 am to 4:00 pm.
- Water service will be turned off for Businesses on Dundas Street East on Monday, October 26, 2026, at 8:00 pm to Tuesday, October 27, 2026, at 4:00 am.
Impacted properties will receive specific notification outlining the date and time of the water service interruption.
Important reminders
- We encourage you to shop and support local.
- Subscribe to receive updates directly to your inbox by adding your email to the Stay Informed box on this page and click ‘Subscribe'.
- All road construction updates and closure information is available at municipal511.ca.
- For a full list of construction projects, visit brant.ca/Construction.