April construction update

Stage 1 of construction began on March 23 and was completed March 30. Stage 2 is currently underway and on schedule. The expected completion for this stage is late summer 2026.

Work locations during stage 2 include: Dundas Street East (both eastbound lanes on the south side of the road) and Paris Road

What has been accomplished

  • CN Rail west side pit installation - complete
  • Dewatering - ongoing
  • Dundas St E asphalt curb and concrete base removals – in-progress
  • Paris Rd sanitary sewer and watermain installation – in-progress

What work is coming up

  • CN Rail east side pit installation
  • Dundas St E asphalt curb and concrete base removals continues
  • Paris Rd and Dundas St watermain works
  • Paris Rd sanitary sewer and watermain installation continues

Traffic Impact reminders

  • Dundas St E – Eastbound and westbound traffic will be reduced to one lane each Eastbound traffic will be unable to make left turns onto Consolidated Dr
  • Governors Rd E - Westbound traffic will be reduced to one lane and unable to make left turns onto Paris Rd
  • Green Lane - Southbound traffic will be unimpeded
  • Paris Rd – There will only be southbound traffic. No northbound traffic permitted

Stage 3

Stage 3 is anticipated to begin late summer 2026 with completion late fall 2026.

Important reminders

Pedestrian access and access to businesses will be maintained throughout the project.

We encourage you to shop and support local.

Road construction updates and closure information is available at municipal511.ca.


Thank you for your patience during this construction season!