October construction update

This multi-year project continues to make great progress as we replace aging underground infrastructure. With the major underground work nearing completion, we are one step closer to the final result: a modernized roadway that improves functionality for drivers, pedestrians, businesses, and future employment growth in the area.

What’s next?

Governors Road will be reduced to one-way on or after October 27 for the sanitary sewer installation. Westbound traffic will be maintained. Eastbound traffic will be detoured. We will keep you posted about the timing of this detour.

Here’s the latest

Paris Road

  • Completed: Gravity sanitary sewer, stormwater main, watermain, road work on the south bound lane, base asphalt, and temporary line painting. Paris Road is open to two-way traffic
  • Underway: Widen road (from the water tower to Oak Park Road), pave entrances and forcemain sanitary sewer (80% complete)
  • Outstanding: Remaining curbs and sidewalk (75% complete with final work to be completed in 2027), final asphalt, and landscape restoration


Governors Road East

  • Completed: Eastbound lane - Sanitary services, watermain, base asphalt, temporary line painting, and curbs
  • Underway: Westbound lane - Asphalt removal, and pave entrances
  • Outstanding: Westbound lane - Sanitary main and service installation, final asphalt, curbs, sidewalk, and landscape restoration.


Dundas St E (Governors Rd E to CN Bridge)

  • Completed: Gravity sanitary sewer, stormwater, watermain, base paving, and temporary line painting
  • Underway: Storm sewer installation at the Green Lane intersection, removal of asphalt on the westbound lane and of the concrete base in centre of the road. Pave entrances, complete remaining curb and sidewalk, asphalt path and concrete sidewalks
  • Outstanding: Storm sewer installations at the intersection of Consolidated Drive, final asphalt, and landscape restoration

CN Bridge Works

  • Completed: Watermain bypass. Remediate watermain failure and installation of new watermain
  • Underway: Watermain commissioning
  • Outstanding: Watermain final connections and surface restorations. Installation of sanitary sewer and stormwater main

Dundas St E (CN Bridge to Curtis Ave)

  • Completed: Storm sewers, watermain installation, asphalt and concrete removals
  • Underway: Watermain commissioning, preparing road base
  • Outstanding: Final asphalt, curb and sidewalk restoration, sanitary sewer installation, and landscape restoration


Upcoming Construction Timeline

By the end of 2026, the ongoing infrastructure project on Dundas Street East, Paris Road, and Oak Park Road in Paris is scheduled to finish Stage 3 (running from September through late fall 2026), wrapping up major underground services and foundational work. Stage 4 is then slated for spring 2027 to finish surface treatments.

Planned Work by the End of 2026 (Stage 3)

  • Complete underground utility and pipe installations
  • Finish sanitary forcemain installations along Paris Road and Oak Park Road (targeted through October 2026 with commissioning in early November)
  • Transition out of major excavation phases leading into late fall 2026


Remaining Work for 2027 (Stage 4)

  • Place the final surface asphalt layer
  • Complete any remaining minor surface works and site restoration


Note: There is a possibility that some works planned for 2026 (storm sewer connection) may need to move to Spring 2027. We will be keep you informed!

Important reminders

  • We encourage you to shop and support local.
  • Subscribe to receive updates directly to your inbox by adding your email to the Stay Informed box on this page and click ‘Subscribe'.
  • All road construction updates and closure information is available at municipal511.ca.
  • For a full list of construction projects, visit brant.ca/Construction.
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>