May construction update
Great news Brant - this project remains on schedule!
We are currently in Stage 2 which began on March 30, 2026 and is expected to be completed in late summer 2026. Stage 3 is expected to start late summer and continue to late fall 2026.
Progress updates
Paris Rd
What is complete?
- Gravity sanitary sewer
- Road base on the southbound lane
- Final watermain connections in the intersection of Dundas St E and Paris Rd
What is underway?
- Final watermain connections on the south limits (just beyond the Full Plate)
Dundas St E (Governors Rd E to CN Bridge)
What is complete?
- Gravity sanitary sewer (2025)
- Storm sewer (2025, not including the Paris Road intersection)
- Removal of asphalt and concrete on eastbound lane
What is underway?
- Watermain is currently being installed from Dundas St E/Paris Rd intersection to the CN Bridge
Governors Rd E
What is complete?
- Removal of asphalt and concrete on eastbound lane
- Sanitary services
What is underway?
- Watermain is currently being installed from Dundas St E/Paris Rd intersection to east limits
CN Bridge Works
What is complete?
- Watermain bypass
What is underway?
- Pipe ramming has begun for the casing under the eastbound lanes
Traffic impacts/Detour routes
- Dundas St E – Eastbound and westbound traffic reduced to one lane each. Eastbound traffic unable to make left turns onto Consolidated Dr
- Governors Rd E - Westbound traffic reduced to one lane and unable to make left turns onto Paris Rd
- Green Lane - Southbound traffic unimpeded
- Paris Rd – Only be southbound traffic. No northbound traffic permitted
Important reminders
- Pedestrian access and access to businesses will be maintained throughout the project.
- We encourage you to shop and support local.
- Road construction updates and closure information is available at municipal511.ca.
Thank you for your patience during this construction season!