Project update - February 2026
The Downtown Dig project is expected to progress well throughout the 2026 construction season. The County encourages locals and visitors to support businesses and shop local.
As with all construction activities, timelines shift as unexpected issues arise and/or extended weather events occur.
As listed below under “Impacts”, it is important to specifically highlight that Grand River St. N between Mechanic St. to William St. will remain closed until all work for the 2026 Dig project is complete including the William St. intersection and the work north to Charlotte St. Detours will be posted.
Proposed Start Date
- Spring 2026 (tentative April - weather dependent)
Expected Completion Date
- Late summer/Early fall 2026
Scope
- Grand River St. North (Mechanic St. to William St.)
- Intersection: Grand River St. North and William St.
- Grand River St. North (William St. to Charlotte Street)
- William Street (Grand River St. N to Grand River Bridge)
Purpose
The purpose of this road reconstruction is to:
- Replace critical infrastructure (water, sewers) and upgrade utilities (gas, electrical etc.) under the roads
- Road re-construction
- Widen sidewalks to enhance pedestrian experience
- Update streetscape such as lamp posts, benches, trees
- Increase accessibility features such as roll over curbs
- Enhance climate resiliency with tree canopy
Impact
- Closure of Grand River St. N (Mechanic St. to Charlotte St.) - Will remain closed to through traffic until all work is complete. Access to businesses from Charlotte south to the work zone will be maintained (i.e., post office, dental office).
- Intersection closure to vehicles - William Street and Grand River St. N. Pedestrian access will be maintained.
- Detour routes will be shared and posted prior to the Dig commencing
Outstanding work for 2026
Grand River St. N (Mechanic St. to William St.):
- Hydro work at Cobblestone Commons and tap box replacements
- Concrete planter boxes
- Continued brick work
- Surface asphalt paving and line painting
Grand River Street North (William St. intersection and William St. to Charlotte St.):
| Traffic signal removal | Traffic signal installation including conduit, pole installation, wiring and controller |
| Streetlight removal | Hydro replacement including primary and secondary in conduit and pull boxes |
| Asphalt removal | Road base construction |
| Curb and sidewalk removal | Sidewalk installation |
| Temporary sewage bypass pumping | Soil cell installation of trees |
| Sanitary sewer replacement | Curb installation |
| Sewer siphon chamber replacements at each end of the William Street Bridge | Planter box installation |
| Storm sewer replacement | Interlocking stone installation |
| Watermain replacement | Asphalt paving |
| Fiber optic conduit installation (for future) | Garden plantings |
| Streetlight installation includes conduit installation, pole installation and wiring | Installation of benches, bike racks and waste receptacles |
Special feature: The 2026 Downtown Paris Promenade
As part of the 2026 phase of the Downtown Dig project, Grand River Street North from Mechanic Street to William Street will be required to close again to permit full reconstruction of the intersection. The County of Brant will plan a temporary pedestrian focused promenade that will activate the closed section of street once construction work in this area is completed (anticipated to begin in June).
The purpose of the 2026 Paris Promenade is to create a warm, welcoming, and vibrant public space that encourages both residents, visitors, and businesses to embrace the temporary street closure. The promenade will offer opportunities for gathering, programming, and recreation, and aims to foster a lively atmosphere that helps maintain business activity throughout the construction period.
Thank you for your patience during the 2026 construction season!