Phase 1: West River Street Reconstruction Begins April 7, 2025

As part of Phase 1 in the Downtown Dig project, the full road reconstruction along West River Street, including replacement of watermain, storm, sanitary sewer, and road resurfacing, begins on Monday, April 7, 2025.

Location: West River Street between Mechanic Street and Broadway Street West

Work Dates: Monday, April 7 to late July 2025, end date to be determined

Work Preformed by: BEECH Infrastructure Group Ltd. for County of Brant

Details:

  • No through traffic
  • Local access will be maintained
  • Emergency access will be maintained
  • Signage will be posted, and a flag person will direct traffic when require
  • Non-local motorists are encouraged to take alternative traffic route

Please refer to Municipal 511 municipal511.ca for the most up-to-date traffic information regarding road construction and closures.

To learn more about the Downtown Dig:

  • Subscribe to this page for updates by clicking 'Subscribe' on the Stay Informed box
  • Follow The Downtown Dig on Facebook and Instagram
  • Visit brant.ca/DowntownDig

It is our goal to minimize any inconvenience to our residents. Thank you for your patience and understanding as we build a better downtown Paris.

Share Phase 1: West River Street Reconstruction Begins April 7, 2025 on Facebook Share Phase 1: West River Street Reconstruction Begins April 7, 2025 on Twitter Share Phase 1: West River Street Reconstruction Begins April 7, 2025 on Linkedin Email Phase 1: West River Street Reconstruction Begins April 7, 2025 link