Downtown Dig Progress Update: September 12
We’re moving into the final stages of Phase 2a and 2b of the Downtown Dig! Much of the major infrastructure work is now complete, and crews are focusing on finishing touches that will bring us closer to a renewed and revitalized downtown.
Work done the past two weeks
- Sanitary sewer services to buildings 100% complete
- Remaining catchbasin installations and storm sewer system 100% complete
- Bell works 100% complete
- Foundation restoration 98% complete, surface parging remains
- Other identified foundation repairs ongoing
- Lisa's Way walkway restored, planter box area remains
- Excavation for road base 100% complete
- Road base gravel placement 50% complete
- Landscaping work has commenced
- Streetlight conduit installation has commenced
- Hydro works Ongoing
Next 2 weeks
- Hydro works continue
- Landscaping works continue
- Streetlight conduit installation continues
- Foundation restoration work will be complete
- Other identified foundation repairs will be complete
- Curb installation to commence
- Sidewalk installation to commence.
Thank you to our residents, businesses, and visitors for your continued patience and support throughout this project — the end result is just around the corner!
Stay connected and informed
✔ Follow the Downtown Dig and the Downtown Paris BIA (@dtparisontario) on Facebook and Instagram
✔ Subscribe for project updates and explore detour maps, phase details, and more on this page
✔ Visit www.brant,ca/DowntownDig for additional resources
✔ Refer to for the most up-to-date traffic information regarding road construction and closures at www.municipal511.ca.