Accomplishments from the last two (2) weeks include:
- Street light conduit - 95%
- Hydro primary line - 95%
- Cobblestone Commons investigation for hydro - 100% complete
- Road base gravel placement - 85% complete
- West side curb - 100% complete
- Landscaping - 20% complete
Anticipated work over the next two (2) weeks include:
- Street light work continues
- Street light poles on west side are expected to arrive shortly and will be installed
- Hydro
- Primary line work continues
- Vault work southeast of Grand River Street North and William Street to be completed
- Service line connecting to businesses to commence October 14, 2025
- Landscaping to continue
- West side planter box to commence
- Curb installation on east side to commence
- Removal of the existing sidewalk on the east side continues
Thank you for your continued patience! Please continue to support our community by shopping and supporting local!
Follow the Downtown Dig on Facebook and Instagram for updates!
Share Downtown Dig Progress Update - October 10, 2025 on Facebook
Share Downtown Dig Progress Update - October 10, 2025 on Twitter
Share Downtown Dig Progress Update - October 10, 2025 on Linkedin
Email Downtown Dig Progress Update - October 10, 2025 link