Downtown Dig Progress Update - August 15

What’s been done (last 2 weeks)

  • Watermain services (main to curbstop) - 90% completed
  • Watermain services (curbstop to building) - 50% completed
  • Sanitary services to building connections - 50% completed
  • Hydro work started


Coming up (next 2 weeks)

  • Water services from main to curbstop continues
  • Water services from curbstop to building continues
  • Sanitary service connection to building continues
  • Hydro work continues


Lisa's Way Update

  • Lisa's Way storm repair next week from Monday, August 18 to Thursday, August 21 (weather depending)
  • Midblock crosswalk will be shifted shortly North of current location
  • Public washrooms will be temporarily unavailable within the duration of the work and portable washrooms will be provided.
  • South row of parking behind BMO will be temporarily unavailable within the duration of the work.


During the Dig, sidewalks, crosswalks, and access to your favourite businesses and establishments will remain open — though occasional changes may occur due to construction activities.

As always, we encourage you to think local and shop in Downtown Paris. The heart of our community thrives with your support.


Stay connected and informed


Thank you for your continued patience as we work to upgrade the infrastructure in Downtown Paris.