Downtown Dig Progress Update - August 1

Highlights from the last two weeks

  • Watermain disinfection & testing – Complete!
  • Watermain is now live at William Street & the Grand River Street North intersection
  • Water service (main to curbstop): 66% complete
  • Water service (curbstop to building): 7% underway
  • Storm sewer system: COMPLETE!


What's coming up next

  • Water service work continues
  • Sanitary service connections begin
  • Hydro work at William Street & Grand River Street North (Southeast corner) begins after the long weekend


Additional timeline information will be shared as it becomes available.

During the Dig, sidewalks, crosswalks, and access to all your favourite businesses and establishments remain open – with the occasional changes due to construction activities.

As always, we encourage you to think local, and shop in Downtown Paris. The heart of Paris needs the support of our local community!


Stay connected and informed

  • Follow the Downtown Dig and Downtown Paris, Ontario on Facebook and Instagram
  • Subscribe for updates by clicking 'Subscribe' on the Stay Informed box on this page
  • Visit brant.ca/DowntownDig for additional resources
  • Refer to Municipal 511 at municipal511.ca for the most up-to-date traffic information regarding road construction and closure


Thank you for your continued patience as we work to upgrade the infrastructure in Downtown Paris.

Share Downtown Dig Progress Update - August 1 on Facebook Share Downtown Dig Progress Update - August 1 on Twitter Share Downtown Dig Progress Update - August 1 on Linkedin Email Downtown Dig Progress Update - August 1 link
#<Object:0x00000000399fdf88>