Downtown Dig Progress Update - June 19

Here’s what’s been happening over the past 2 weeks in Downtown Paris:
  • Oil and Grit Separator has been fully installed
  • Sanitary sewer main system (south of William St): 3/4 complete
  • Water main system (south of William St): 1/5 complete
Coming up next:
  • Sanitary main work expected to wrap up by the end of next week (weather permitting)
  • Storm main system installation will follow
  • Water main work will continue, with service connections to follow shortly after
For the services listed above this does not include the individual service connections to properties. These will be done at a later date.
The Navacon team will be offsite tomorrow (June 20) for required training and will not be onsite Monday, June 30 as several Canada Day celebrations take place in Downtown Paris! Be sure to follow the Downtown Dig on Facebook and Instgram for project updates, highlights and more Also follow Downtown Paris, Ontario to learn more about the exciting events planned.
Thank you for your continued patience and support during the Downtown Dig! To learn more about the Dig visit brant.ca/DowntownDig
Share Downtown Dig Progress Update - June 19 on Facebook Share Downtown Dig Progress Update - June 19 on Twitter Share Downtown Dig Progress Update - June 19 on Linkedin Email Downtown Dig Progress Update - June 19 link