Broadway West and West River Reconstruction

The County of Brant is planning infrastructure improvements along Broadway Street West and West River Street in Paris.

The project will replace and improve important underground infrastructure, including wastewater and stormwater services, and install a new watermain. A new multi-use path will also be added, giving people a safer and more comfortable space to walk, cycle and use other active transportation where one doesn't currently exist.

The new watermain will help support future residential, commercial and industrial growth in south Paris and is being funded through development charges.

What to expect: Traffic impacts and road closures

Beginning in early October, West River Street will close to through traffic between Charlotte Street and Broadway Street West so storm sewer work can begin. The road will remain open to local traffic.

There will be an overlap of approximately two weeks between West River Street construction beginning and the Downtown Dig construction wrapping up for the season.

The County was notified that a gas main is required to be relocated on Broadway Street West. Two way traffic will be maintained to help manage traffic flow. There may be minor traffic impacts, so please allow extra time and plan your route accordingly.

As construction progresses:

  • West River Street will remain open to local traffic only during its active construction phase.
  • Broadway Street West will be fully closed to traffic during its active construction phase. Access to residential properties will be maintained.
  • Broadway Street West and West River Street will not be closed at the same time. One route will remain open throughout construction.

Work will also take place beneath the CN railway tracks. This work will require a temporary full closure of either Market Street or Broadway Street. Access to Railway Street will be maintained. More information about the closure and timing will be shared once CN has approved the work plan.

The County will continue to coordinate construction and traffic impacts between this project and the Downtown Dig. Until Grand River Street North and William Street reopen, and two way traffic will be maintained to help manage traffic through the area.

Additional information about construction timing, closures and traffic impacts will be shared as work progresses.

Local access maintained

While temporary access reductions or restrictions may happen at specific times near Railway Street, the County plans to maintain consistent access to:

  • Railway Street
  • Paris Transfer Station
  • Penman’s Pass parking lot

Stay informed

Progress updates will be posted on this page. Subscribe to receive updates by adding your email to the Stay Informed box on this page and click ‘Subscribe'.

The County of Brant is planning infrastructure improvements along Broadway Street West and West River Street in Paris.

The project will replace and improve important underground infrastructure, including wastewater and stormwater services, and install a new watermain. A new multi-use path will also be added, giving people a safer and more comfortable space to walk, cycle and use other active transportation where one doesn't currently exist.

The new watermain will help support future residential, commercial and industrial growth in south Paris and is being funded through development charges.

What to expect: Traffic impacts and road closures

Beginning in early October, West River Street will close to through traffic between Charlotte Street and Broadway Street West so storm sewer work can begin. The road will remain open to local traffic.

There will be an overlap of approximately two weeks between West River Street construction beginning and the Downtown Dig construction wrapping up for the season.

The County was notified that a gas main is required to be relocated on Broadway Street West. Two way traffic will be maintained to help manage traffic flow. There may be minor traffic impacts, so please allow extra time and plan your route accordingly.

As construction progresses:

  • West River Street will remain open to local traffic only during its active construction phase.
  • Broadway Street West will be fully closed to traffic during its active construction phase. Access to residential properties will be maintained.
  • Broadway Street West and West River Street will not be closed at the same time. One route will remain open throughout construction.

Work will also take place beneath the CN railway tracks. This work will require a temporary full closure of either Market Street or Broadway Street. Access to Railway Street will be maintained. More information about the closure and timing will be shared once CN has approved the work plan.

The County will continue to coordinate construction and traffic impacts between this project and the Downtown Dig. Until Grand River Street North and William Street reopen, and two way traffic will be maintained to help manage traffic through the area.

Additional information about construction timing, closures and traffic impacts will be shared as work progresses.

Local access maintained

While temporary access reductions or restrictions may happen at specific times near Railway Street, the County plans to maintain consistent access to:

  • Railway Street
  • Paris Transfer Station
  • Penman’s Pass parking lot

Stay informed

Progress updates will be posted on this page. Subscribe to receive updates by adding your email to the Stay Informed box on this page and click ‘Subscribe'.

  • Construction Notice: Storm sewer repairs begin September 24, 2026

    Starting September 24, 2026, work will begin with repairs to the storm sewer outlet channel between Broadway Street West and the Nith River at Penman’s Pass.

    Changes during construction period

    • Intersection impacts: Initially intersections will not be impact but look for future updates throughout the project
    • Road or sidewalk impacts: Road and sidewalks will not be impacted as part of the first stage of the work but look for future updates throughout the project
    • Detour routes: None
    • Noise/light: Heavy equipment and dump trucks will be operating in the area in compliance with the Noise By-law
    • Parking: Half of the Penman’s

    Starting September 24, 2026, work will begin with repairs to the storm sewer outlet channel between Broadway Street West and the Nith River at Penman’s Pass.

    Changes during construction period

    • Intersection impacts: Initially intersections will not be impact but look for future updates throughout the project
    • Road or sidewalk impacts: Road and sidewalks will not be impacted as part of the first stage of the work but look for future updates throughout the project
    • Detour routes: None
    • Noise/light: Heavy equipment and dump trucks will be operating in the area in compliance with the Noise By-law
    • Parking: Half of the Penman’s Pass parking lot off Broadway St West will be closed for use by the Contractor as a staging area for the work.
    • Access (personal driveways, services or amenities): Stair access to the Penman’s Pass trail and bridge will be closed. Paved trail access will remain open, but pedestrians are cautioned as this route will be used for access by heavy construction equipment. A spotter will travel with the construction equipment when moving or working on the trail.
    • Garbage: No impacts.


    Map of construction area

    Contractor: Regional Sewer and Watermain Ltd.


    Stay informed

    Subscribe for updates by adding your email to the Stay Informed box on this page and click ‘Subscribe'.

    Please visit brant.ca/Construction for all project notices and refer to municipal511.ca for the most up-to-date information regarding road construction and closures.

  • Thank you for attending the Open House on September 21

    Thank you to everyone who joined us last night for the Broadway Street West and West River Street Reconstruction Public Open House.

    We appreciate you taking the time to learn about the project, speak with the project team and share your questions and comments.

    As the project moves forward, we will continue to share construction, traffic and project updates on this page. Subscribe to have project updates sent directly to your email by adding your email address to the to the Stay Informed box on this page and click ‘Subscribe'.

    Thank you to everyone who joined us last night for the Broadway Street West and West River Street Reconstruction Public Open House.

    We appreciate you taking the time to learn about the project, speak with the project team and share your questions and comments.

    As the project moves forward, we will continue to share construction, traffic and project updates on this page. Subscribe to have project updates sent directly to your email by adding your email address to the to the Stay Informed box on this page and click ‘Subscribe'.

  • Attend the September 21 Open House

    You're invited to attend a Public Information Open House in September.

    • Monday, September 21, 2026
    • 5:00 to 7:00 pm
    • County of Brant Council Chambers, 7 Broadway Street West, Paris

    This will be a drop in event to give community members an opportunity to learn more about the project, view project information, and speak directly with members of the project team.

    Can't make it? Please share your comments and questions with us.

    You're invited to attend a Public Information Open House in September.

    • Monday, September 21, 2026
    • 5:00 to 7:00 pm
    • County of Brant Council Chambers, 7 Broadway Street West, Paris

    This will be a drop in event to give community members an opportunity to learn more about the project, view project information, and speak directly with members of the project team.

    Can't make it? Please share your comments and questions with us.

Page last updated: 28 Sep 2026, 09:20 AM