Overview and proposed uses

    What commercial uses are proposed?

    The upper level is envisioned as an event venue run by an independent operator, while the main floor is intended for County activities. The County would also be able to use the upper floor at less busy times.

    Why is this plan suitable while the library was not?

    The former central library concept required a much larger addition and faced site constraints and escalating costs. Its estimate rose from $12.5 million in 2021 to more than $41 million after tenders in late 2024. Council did not revisit the library concept after its early-2025 decisions.

    How does the project comply with the original Bawcutt donation agreement?

    The plan includes dedicated arts, culture and community space, while allowing commercial activity to help manage operating costs. The County retains day-to-day authority under the agreement. The Bawcutt Centre Advisory Committee unanimously endorsed the proposal on May 12, 2026.

Project funding and costs

    How much is the project costing and who is paying?

    Council has committed up to $9.5 million for the project, approximately $5 million less than the estimated cost of proceeding without Wingbury. Staff have also been directed to pursue government grants to offset the expense.

    How will fundraising work?

    The County plans to explore grants and community fundraising now that a renovation plan and municipal funding are approved. Fundraising since the original $1 million gift in 2015 has been limited; a donor recognition and fundraising program is to be developed.

    How are taxpayers protected if costs increase?

    The approved budget is capped at $9.5 million unless Council authorizes additional funding. The project includes contingency funding, and the County and Wingbury intend to adjust project scope if necessary to remain within budget.

Partnerships and project planning

    What is the partnership with Wingbury Properties?

    Wingbury Properties is volunteering project-management expertise, drawing on its experience restoring historic properties such as Wincey Mills. It will also help identify a third-party operator for the proposed event space. The County states that Wingbury is not receiving a financial benefit from the arrangement.

    How has parking been addressed?

    The current concept is smaller than the former library proposal: under 10,000 square feet rather than 39,000 square feet. It anticipates 63 on-site spaces, including 4 accessible spaces, which exceeds the parking requirements under the County’s Zoning By-law. 

    How will the building's heritage features be protected?

    Heritage-related changes require a heritage permit and review through the municipal heritage process. Restoration will prioritize designated features, including upper-hall beams, cross-bracing and windows; non-heritage elements may be replaced with more economical alternatives.

    What are the next steps and project timeline?

    Staff and Wingbury are finalizing project details and pursuing required planning and building approvals. Important pre-winter work includes roof replacement. Design and renovations were estimated to take 18–24 months, with a public opening anticipated in 2028.

Council decisions and information

    When and where was this proposal discussed?

    The proposal was presented to The Bawcutt Centre Advisory Committee on May 12, 2026, and to Council on May 26, 2026. Discussions occurred in closed session under the Municipal Act because they involved a possible property lease and related directions.

    Where can residents read the reports, agreements and Council decisions?

    The County indicated that more information would be released. Some earlier reports include confidential proprietary material from the expression-of-interest process and cannot be shared in full.